  • Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
  • Ninemile north headwall placed and backfilled. Eightmile has been backfilled.
  • Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
  • Patterned concrete median islands are being placed east of Black Cat.
  • Asphalt paving portions of the north and south side of Ustick complete.
  • Weather dependent, the contractor is working towards having the remaining paving sections on Ustick complete in the next couple of weeks.
  • City of Meridian sewer and water line installation is complete.
  • East headwall of Eightmile has been placed and backfilled.