July 18, 2025
- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi is closed south of Ustick Road
- Contractor is working to complete the intersection prior to school starting, August 13th.
- Ustick remains open:
- Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish
- Eightmile irrigation:
- Irrigation is complete for the season.
- Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
- City of Meridian bypass was executed this week. No issues.
- HDPE sewer is complete.
Share July 18, 2025 on Facebook
Share July 18, 2025 on X (formerly Twitter)
Share July 18, 2025 on Linkedin
Email July 18, 2025 link
This project is substantially complete.