July 25, 2025

  • Black Cat Road is open north of Ustick Road.
  • Black Cat Road is closed south of Ustick Road. Naomi is open to Ustick Road.
  • Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
  • Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
  • Rutledge has been sleeved for sewer line install. Curb and gutter and sidewalk placements ongoing on the north side of Ustick. HDPE bypass pipe to be removed.
  • Contractor is focusing on the Naomi intersection to be complete before school starts, August 13th.
Share July 25, 2025 on Facebook Share July 25, 2025 on X (formerly Twitter) Share July 25, 2025 on Linkedin Email July 25, 2025 link

This project is substantially complete.