June 20, 2025
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open:
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation:
- Irrigation is complete for the season.
- Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
- HDPE Pipe welding is ongoing for the City of Meridian’s sewer bypass.
Share June 20, 2025 on Facebook
Share June 20, 2025 on X (formerly Twitter)
Share June 20, 2025 on Linkedin
Email June 20, 2025 link
This project is substantially complete.