  • Black Cat Road is closed north of Ustick Road.
  • Black Cat Road is open south of Ustick Road.
  • Aspenstone Street is closed at Black Cat Road.
  • Ustick remains open:
    • Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
  • Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
  • Eightmile irrigation:
    • Irrigation is complete for the season.
  • Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
    • Rutledge has been sleeved for sewer line install.
  • Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
  • Concrete paving placements will be ongoing.
    • Placement schedule will be every Monday and Wednesday moving forward.
  • HDPE Pipe welding is ongoing for the City of Meridian’s sewer bypass.