June 26, 2026

26 Jun 2025
  • Black Cat Road is closed north of Ustick Road.
  • Black Cat Road is open south of Ustick Road.
  • Aspenstone Street is closed at Black Cat Road.
  • Ustick remains open: o Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
  • Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
  • Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
  • Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
  • Concrete paving placements will be ongoing. Placement schedule will be every Monday and Wednesday moving forward.
  • Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete. HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.