June 6, 2025

  • Black Cat Road is closed north of Ustick Road.
  • Black Cat Road is open south of Ustick Road.
  • Aspenstone Street is closed at Black Cat Road.
  • Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
  • Irrigation and seepage bed installation is nearly complete.
  • Roadway and sidewalk demo complete, and grade prep complete on the north side of Ustick for curb, gutter, and sidewalk.
  • Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
  • Rutledge has been sleeved for sewer line install.
  • Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
  • Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
  • Concrete paving placements will be ongoing.
  • Placement schedule will be every Monday and Wednesday moving forward.
Share June 6, 2025 on Facebook Share June 6, 2025 on X (formerly Twitter) Share June 6, 2025 on Linkedin Email June 6, 2025 link

This project is substantially complete.