June 6, 2025
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete.
- Roadway and sidewalk demo complete, and grade prep complete on the north side of Ustick for curb, gutter, and sidewalk.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.