March 14, 2025

  • Black Cat Road is closed south of Ustick Road.
  • Ustick remains open:
  • Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
  • Irrigation and seepage bed installation is ongoing.
  • Roadway and sidewalk demo and prep are ongoing on the north side of Ustick.
  • Eight mile irrigation: Concrete irrigation splitter box placements completed this week.
  • Utility relocations are complete.
  • Temporary precast sections have been set.
  • Irrigation work, apart from Ninemile (sleeved), is nearly complete in preparation for the City’s sewer bypass.
  • Precast box fabrication complete for this season.
Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link

This project is substantially complete.

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>