March 19, 2026
- Black Cat remains closed south of Ustick Rd.
- Concrete paving section and sidewalk placements remain.
- City of Meridian sewer and water line installation is complete.
- Water Control Vault commissioning work is ongoing.
- Underground electrical work and signal pole bases are complete.
- Electrical contractor is working on the wiring in the signal cabinets.
- Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, will continue as weather allows.
- Concrete sidewalk placements on South Black Cat started again this week.
Share March 19, 2026 on Facebook
Share March 19, 2026 on Twitter
Share March 19, 2026 on Linkedin
Email March 19, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends