March 20, 2025
- Black Cat Road is closed south of Ustick Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep are ongoing on the north side of Ustick.
- Eight Mile irrigation: Concrete irrigation splitter box placements completed this week.
- Utility relocations are complete.
- Temporary precast sections have been set.
- Irrigation work, apart from Nine mile (sleeved), is nearly complete in preparation for the City’s sewer bypass.
- Precast box fabrication complete for this season.
Share March 20, 2025 on Facebook
Share March 20, 2025 on X (formerly Twitter)
Share March 20, 2025 on Linkedin
Email March 20, 2025 link
This project is substantially complete.