March 28, 2025

28 Mar 2025
  • Black Cat Road is closed north of Ustick Road.
  • Black Cat Road is open south of Ustick Road.
  • Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo and prep are ongoing on the north side of Ustick.
  • Eight Mile irrigation: Concrete irrigation splitter box placements completed this week. Waiting on lids. Utility relocations are complete. Temporary precast sections have been set. Irrigation work, apart from Nine Mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.