March 6, 2026

  • Black Cat remains closed south of Ustick Rd.
  • Concrete paving section and sidewalk placements remain.
  • City of Meridian sewer and water line installation is complete.
  • Water Control Vault commissioning work is ongoing.
  • Underground electrical work and signal pole bases are complete.
  • Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, started this week and will continue as weather allows.