- Black Cat, south of Ustick Rd was re-opened on April 30th.
- City of Meridian sewer and water line installation is complete.
- Water Control Vault commissioning work is ongoing.
- Underground electrical work and signal pole bases are complete.
- The electrical contractor is working on the wiring in the signal cabinets.
- Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, are complete.
- Concrete sidewalk placements on South Black Cat are complete.
- Concrete pavement on the south leg of Black Cat will be completed this week.
- Asphalt paving is complete.
Share May 1, 2026 on Facebook
Share May 1, 2026 on Twitter
Share May 1, 2026 on Linkedin
Email May 1, 2026 link
This project is substantially complete.