May 2, 2025
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter is scheduled for next week.
Share May 2, 2025 on Facebook
Share May 2, 2025 on Twitter
Share May 2, 2025 on Linkedin
Email May 2, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends