November 14, 2025
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile.
- Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
- Patterned concrete median islands are being placed east of Black Cat.
- Asphalt paving portions of the north side of Ustick complete (bottom lift only).
- City of Meridian sewer and water line installation continues at Black Cat/Ustick.
- Concrete paving south side of Ustick and Black Cat intersection complete.