November 22, 2024

  • Contractor has completed implementing traffic control on the project and throughout the southern neighborhoods.
  • Black Cat Road is closed south of Ustick Road.
  • Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.