November 7, 2025
- Black Cat Road is open north of Ustick Road. Black Cat Road is closed south of Ustick Road. Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: oTraffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile and Ninemile irrigation: Irrigation work started again on October 20th at both Eightmile and Ninemile. oThe remaining precast box sections for Eightmile have been delivered.Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed. Excavation activities are complete on the south side of Ustick. Grade prep on the south side of Ustick ongoing. Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.
Share November 7, 2025 on Facebook
Share November 7, 2025 on Twitter
Share November 7, 2025 on Linkedin
Email November 7, 2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends