October 10, 2025
- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish Eightmile irrigation: Irrigation is complete for the season. The remaining precast box sections are planning to be delivered end of October. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only).
- City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
- Excavation activities are ongoing on the south side of Ustick.
- Grade prep on the south side of Ustick ongoing.
- Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.
Share October 10, 2025 on Facebook
Share October 10, 2025 on Twitter
Share October 10, 2025 on Linkedin
Email October 10, 2025 link
This project is substantially complete.