October 10, 2025

  • Black Cat Road is open north of Ustick Road.
  • Black Cat Road is closed south of Ustick Road.
  • Naomi has reopened on the south side to Ustick Road for school access.
  • Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish Eightmile irrigation: Irrigation is complete for the season. The remaining precast box sections are planning to be delivered end of October. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only).
  • City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
  • Excavation activities are ongoing on the south side of Ustick.
  • Grade prep on the south side of Ustick ongoing.
  • Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.