October 17, 2025

  • Black Cat Road is open north of Ustick Road.
  • Black Cat Road is closed south of Ustick Road.
  • Naomi has reopened on the south side to Ustick Road for school access.
  • Ustick remains open: o Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open.
  • Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish. Eightmile irrigation: o Irrigation is complete for the season. The remaining precast box sections are planning to be delivered end of October.
  • Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
  • Excavation activities are ongoing on the south side of Ustick.
  • Grade prep on the south side of Ustick ongoing.
  • Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.
Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 link