April 10, 2026

  • Roadway milling/removal is complete for a portion of Ustick.
  • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
  • Contractor continues setting baskets for the bottom lift(s) of the retaining wall.
  • Contractor is now above ordinary high water.
  • Clearing and grubbing work is ongoing.
  • Seepage bed installation work is ongoing.
  • Contractor continues placement of sidewalk/MUP on the east end of the project.
  • Utility relocations are ongoing.