Share December 18, 2025 on Facebook
Share December 18, 2025 on Linkedin
Email December 18, 2025 link
- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Roadway milling/removal is complete for a portion of Ustick.
- Contractor is staging and preparing for the dewatering operation of Five Mile Creek.
- City of Meridian sewer bypass and CIPP lining installation started this week.
- Clearing and grubbing work is ongoing.
Share December 11, 2025 on Facebook
Share December 11, 2025 on Linkedin
Email December 11, 2025 link
- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Roadway milling/removal is complete for a portion of Ustick.
- Contractor is staging and preparing for the dewatering operation of Five Mile Creek.
- Contractor is staging and preparing for the City of Meridian sewer bypass – expected to start Dec 15.
- Clearing and grubbing work is ongoing.
Share December 4, 2025 on Facebook
Share December 4, 2025 on Linkedin
Email December 4, 2025 link
- Ustick Road closure started December 1st o Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Roadway milling/removal has started on Ustick.
- Contractor is staging and preparing for the dewatering operation of Five Mile Creek.
- Contractor is staging a preparing for the City of Meridian sewer bypass.
Share Detour Map & Information on Facebook
Share Detour Map & Information on Linkedin
Email Detour Map & Information link

Beginning Monday, Ustick Road will close between Ten Mile Road and Linder Road as work begins on ACHD’s Ustick Road, Ten Mile to Linder project.
During the closure, commuters should use McMillan Road to the north or Cherry Lane to the south to get around the closure (see detour map). Local access will be maintained for residents along the corridor.
The closure is expected to last until summer 2026.
The work is part of ACHD's Ustick, Ten Mile to Linder project. Once complete, Ustick Road will be widened to five travel lanes, and a new traffic signal will be installed at Ustick Road and Towerbridge Way. The project also includes constructing ten-foot multi-use pathways on either side of Ustick Road, along with other improvements.
Share November 20, 2025 on Facebook
Share November 20, 2025 on Linkedin
Email November 20, 2025 link
- Ustick closures are anticipated to start December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. are expected to start being installed the week of November 24th.
Share Construction to start late October 2025 on Facebook
Share Construction to start late October 2025 on Linkedin
Email Construction to start late October 2025 link
ACHD will begin widening Ustick Road from Ten Mile to Linder in late October to improve traffic flow and increase safety. Work is expected to finish in late 2026.*
Share Fall 2022 Public Outreach on Facebook
Share Fall 2022 Public Outreach on Linkedin
Email Fall 2022 Public Outreach link
This project's second round of public outreach closed on November 3, 2022. View the comment summary and infographic below!
Share Winter 2020 Public Outreach on Facebook
Share Winter 2020 Public Outreach on Linkedin
Email Winter 2020 Public Outreach link
In the winter of 2020, we asked neighbors to tell us about their experiences using Ustick Road from Ten Mile Road to Linder Road while driving, walking and/or bicycling, as well as what they thought our priorities should be as we develop the design. The survey closed January 7, 2021. View the public outreach comment summary below!