August 14, 2026


  • City of Meridian water work is ongoing – Mainline is complete, services to follow.
  • Seepage bed installation work is complete.
  • Contractor continues placement of sidewalk/MUP on the east end of the project.
  • Utility relocations are complete for this phase of work.
  • Placements of the concrete moment slab along the retaining wall are on-going.
  • Island curb placements are ongoing.
  • Contractor paved on the south side of Ustick and has reopened to traffic (one lane each direction) from Linder to Ten Mile.
  • Contractor is continuing to subgrade the western half of the project.