August 14, 2026
- City of Meridian water work is ongoing – Mainline is complete, services to follow.
- Seepage bed installation work is complete.
- Contractor continues placement of sidewalk/MUP on the east end of the project.
- Utility relocations are complete for this phase of work.
- Placements of the concrete moment slab along the retaining wall are on-going.
- Island curb placements are ongoing.
- Contractor paved on the south side of Ustick and has reopened to traffic (one lane each direction) from Linder to Ten Mile.
- Contractor is continuing to subgrade the western half of the project.