December 11, 2025

  • Ustick Road closure started December 1st.
  • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
  • Roadway milling/removal is complete for a portion of Ustick.
  • Contractor is staging and preparing for the dewatering operation of Five Mile Creek.
  • Contractor is staging and preparing for the City of Meridian sewer bypass – expected to start Dec 15.
  • Clearing and grubbing work is ongoing.
Share December 11, 2025 on Facebook Share December 11, 2025 on Twitter Share December 11, 2025 on Linkedin Email December 11, 2025 link
#<Object:0x00007f6ea0271300>