December 18, 2025

  • Ustick Road closure started December 1st.
  • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
  • Roadway milling/removal is complete for a portion of Ustick.
  • Contractor is staging and preparing for the dewatering operation of Five Mile Creek.
  • City of Meridian sewer bypass and CIPP lining installation started this week.
  • Clearing and grubbing work is ongoing.