February 12, 2026
- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Roadway milling/removal is complete for a portion of Ustick.
- Contractor has completed setting the bypass pipe down Five Mile Creek.
- Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
- Contractor continues setting baskets for the bottom lift(s) of the retaining wall.
- Work on the City of Meridian sewer install and bypass at Glennfield Way and Ustick continues.
- Clearing and grubbing work is ongoing.
- Utility relocations are ongoing.