February 5, 2026
- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Roadway milling/removal is complete for a portion of Ustick.
- Contractor has completed setting the bypass pipe down Five Mile Creek.
- Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
- Contractor has started setting baskets for the bottom lift(s) of the retaining wall.
- City of Meridian sewer bypass and CIPP lining installation is complete.
- Work on the City of Meridian sewer install and bypass at Glennfield Way and Ustick continues.
- Clearing and grubbing work is ongoing.
- Utility relocations are ongoing.
Share February 5, 2026 on Facebook
Share February 5, 2026 on Twitter
Share February 5, 2026 on Linkedin
Email February 5, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends