January 23, 2026

  • Ustick Road closure started December 1st o Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
  • Roadway milling/removal is complete for a portion of Ustick.
  • Contractor has completed setting the bypass pipe down Five Mile Creek.
  • Contactor has started excavating from the east for the retaining wall along Five Mile Creek.
  • City of Meridian sewer bypass and CIPP lining installation is complete.
  • Work on the City of Meridian sewer install and bypass at Glennfield Way and Ustick started this week.
  • Clearing and grubbing work is ongoing.
  • Utility relocations ongoing.