July 1, 2026

  • Contactor has completed the installation of the retaining wall.
  • Contractor has completed the subgrade excavation from east to west along Ustick, and has started importing base material.
  • City of Meridian water work is ongoing – Mainline is complete, services to follow.
  • Seepage bed installation work is complete.
  • Contractor continues placement of sidewalk/MUP on the east end of the project.
  • Utility relocations are ongoing – nearly complete.
  • First placement of the moment slab along the retaining wall is scheduled to be placed next week.