- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Contactor has completed the installation of the retaining wall.
- Contractor has completed the subgrade excavation from east to west along Ustick, and has started importing base material.
- City of Meridian water work is ongoing – Mainline is complete, services to follow.
- Seepage bed installation work is complete.
- Contractor continues placement of sidewalk/MUP on the east end of the project.
- Utility relocations are ongoing – complete.
- First placement of the moment slab along the retaining wall was placed.
- Island curb placements have started.
- Contractor anticipates partial paving on the south side of Ustick next week in preparation for reopening to traffic (one lane each direction) from Linder to Ten Mile.
Share July 17, 2026 on Facebook
Share July 17, 2026 on X (formerly Twitter)
Share July 17, 2026 on Linkedin
Email July 17, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends