July 30, 2026

  • Contactor has completed the installation of the retaining wall.
  • Contractor has completed the subgrade excavation from east to west along Ustick and has started importing base material.
  • City of Meridian water work is ongoing – Mainline is complete, services to follow.
  • Seepage bed installation work is complete.
  • Contractor continues placement of sidewalk/MUP on the east end of the project.
  • Utility relocations are complete for this phase of work.
  • Placements of the concrete moment slab along the retaining wall are on-going.
  • Island curb placements have started.
  • Contractor paved on the south side of Ustick next week in preparation for reopening to traffic (one lane each direction) from Linder to Ten Mile by July 31st.