June 26, 2026

  • Ustick Road closure started December 1st.
  • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
  • Contactor has completed the installation of the retaining wall.
  • Contractor continues to subgrade from east to west along Ustick. City of Meridian water work is ongoing – Mainline is complete, services to follow.
  • Seepage bed installation work is ongoing.
  • Contractor continues placement of sidewalk/MUP on the east end of the project.
  • Utility relocations are ongoing.
  • First placement of the moment slab along the retaining wall is scheduled to be placed this week.
Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>