March 6, 2026
- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Roadway milling/removal is complete for a portion of Ustick.
- Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
- Contractor continues setting baskets for the bottom lift(s) of the retaining wall.
- Work on the City of Meridian sewer install and bypass at Glennfield Way and Ustick continues.
- Clearing and grubbing work is ongoing.
- Utility relocations are ongoing.
Share March 6, 2026 on Facebook
Share March 6, 2026 on Twitter
Share March 6, 2026 on Linkedin
Email March 6, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends