May 29, 2026
- Ustick Road closure started December 1st.
- Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
- Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
- Contractor continues setting baskets for the retaining wall.
- Contractor is now above ordinary high water.
- Contractor has started subgrading from east to west along Ustick.
- City of Meridian water work is expected to start this week.
- Seepage bed installation work is ongoing.
- Contractor continues placement of sidewalk/MUP on the east end of the project.
- Utility relocations are ongoing.