November 6, 2026

  • One lane is open in each direction between Ten Mile Rd and Linder Rd.
  • Placements of the concrete moment slab and parapet wall along the retaining wall are ongoing.
  • Island curb placements are ongoing.
  • The contractor paved the second phase of the project on October 1st (bottom lift). Traffic will still be one lane each direction from Ten Mile to Linder, while they begin to work the southwest section of the project.
  • Contractor continues to excavate the existing roadway section to subgrade on the southwest side of the project.