October 2, 2026
- One lane is open in each direction between Ten Mile Rd and Linder Rd.
- Contractor has completed placement of sidewalk/MUP on the east end of the project.
- Contractor continues to place concrete MUP at various locations along the project.
- Utility relocations are complete for this phase of work.
- Placements of the concrete moment slab along the retaining wall are ongoing.
- Island curb placements are ongoing.
- The contractor paved the second phase of the project on October 1st (bottom lift).
- Traffic will still be one lane each direction from Ten Mile to Linder, while they begin to work the southwest section or the project.