September 11, 2026
- Contractor has completed placement of sidewalk/MUP on the east end of the project.
- Contractor continues to place concrete MUP at various locations along the project.
- Utility relocations are complete for this phase of work.
- Placements of the concrete moment slab along the retaining wall is ongoing.
- Island curb placements are ongoing.
- Contractor paved on the south side of Ustick and has reopened to traffic (one lane each direction) from Linder to Ten Mile.
- Contractor is continuing to subgrade, install pit run, and prep the western half of the project for the next phase of the project.
Share September 11, 2026 on Facebook
Share September 11, 2026 on X (formerly Twitter)
Share September 11, 2026 on Linkedin
Email September 11, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends