September 11, 2026

  • Contractor has completed placement of sidewalk/MUP on the east end of the project.
  • Contractor continues to place concrete MUP at various locations along the project.
  • Utility relocations are complete for this phase of work.
  • Placements of the concrete moment slab along the retaining wall is ongoing.
  • Island curb placements are ongoing.
  • Contractor paved on the south side of Ustick and has reopened to traffic (one lane each direction) from Linder to Ten Mile.
  • Contractor is continuing to subgrade, install pit run, and prep the western half of the project for the next phase of the project.