September 17, 2026

  • One lane is open in each direction between Ten Mile Rd and Linder Rd.
  • Contractor has completed placement of sidewalk/MUP on the east end of the project.
  • Contractor continues to place concrete MUP at various locations along the project.
  • Utility relocations are complete for this phase of work.
  • Placements of the concrete moment slab along the retaining wall are ongoing.
  • Island curb placements are ongoing.
  • Contractor is continuing to subgrade, install pit run, and prep the western half of the project for the next phase of the project.
Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>