11th Street Bikeway

Share 11th Street Bikeway on Facebook Share 11th Street Bikeway on Twitter Share 11th Street Bikeway on Linkedin Email 11th Street Bikeway link

This project is substantially complete. 

Review the story map of the 11th Street project here!

The Ada County Highway District (ACHD) started construction mid-April and is anticipated to finish November of 2022.

ACHD is constructing a bikeway that includes a multi-use pathway thru the Boise High School campus, wayfinding and bikeway signage, enhanced crossings, sharrows, and bike lanes. Suez will also be installing a water line down 11th Street between Heron and Fort streets.

What to expect during construction:

  • Lane restrictions
  • Temporary on-street parking impacts
  • Short-term closures
  • Temporary pedestrian detours
  • Equipment back up alarms and ground vibration
  • General construction noise and dust

Contractors will coordinate with property owners to maintain access during construction and crews will work between 7 a.m. to 7 p.m., unless otherwise approved.

Due to contractor staffing issues and supply-chain shortages, construction schedules could change.

Project Description

The Ada County Highway District (ACHD) designed bikeway improvements for 11th Street from Heron to State to create a continuous connection from the North End and Camel's Back Park to Downtown Boise.

Highlights

  • Rehabilitate the pavement on 11th Street between Washington and Heron Streets.
  • Install enhanced pedestrian crossings at Fort/11th, Hays/11th, and Hays/12th with bicycle push buttons and bulb-outs.
  • Construct a new multi-use pathway through the Boise High School campus with all-way stop intersections at Franklin and Washington streets.
  • A phased approach near Washington Street which will start with painted sharrows (a lane marking that indicates vehicles and cyclists share the road). A future phase may add full bicycle lanes which will remove parking along this section (approximately 10 spaces). This will be determined after coordination with the YMCA and City of Boise.
  • Install new pedestrian-scale lighting at the bulb outs and multi-use pathway.

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Review the story map of the 11th Street project here!

The Ada County Highway District (ACHD) started construction mid-April and is anticipated to finish November of 2022.

ACHD is constructing a bikeway that includes a multi-use pathway thru the Boise High School campus, wayfinding and bikeway signage, enhanced crossings, sharrows, and bike lanes. Suez will also be installing a water line down 11th Street between Heron and Fort streets.

What to expect during construction:

  • Lane restrictions
  • Temporary on-street parking impacts
  • Short-term closures
  • Temporary pedestrian detours
  • Equipment back up alarms and ground vibration
  • General construction noise and dust

Contractors will coordinate with property owners to maintain access during construction and crews will work between 7 a.m. to 7 p.m., unless otherwise approved.

Due to contractor staffing issues and supply-chain shortages, construction schedules could change.

Project Description

The Ada County Highway District (ACHD) designed bikeway improvements for 11th Street from Heron to State to create a continuous connection from the North End and Camel's Back Park to Downtown Boise.

Highlights

  • Rehabilitate the pavement on 11th Street between Washington and Heron Streets.
  • Install enhanced pedestrian crossings at Fort/11th, Hays/11th, and Hays/12th with bicycle push buttons and bulb-outs.
  • Construct a new multi-use pathway through the Boise High School campus with all-way stop intersections at Franklin and Washington streets.
  • A phased approach near Washington Street which will start with painted sharrows (a lane marking that indicates vehicles and cyclists share the road). A future phase may add full bicycle lanes which will remove parking along this section (approximately 10 spaces). This will be determined after coordination with the YMCA and City of Boise.
  • Install new pedestrian-scale lighting at the bulb outs and multi-use pathway.

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete. 

  • January 6, 2023

    Share January 6, 2023 on Facebook Share January 6, 2023 on Twitter Share January 6, 2023 on Linkedin Email January 6, 2023 link
    • Concrete at Pueblo complete.
    • Water work will resume on Hays between 11th and 12th early this year.
    • Power service is complete.
  • December 29, 2022

    Share December 29, 2022 on Facebook Share December 29, 2022 on Twitter Share December 29, 2022 on Linkedin Email December 29, 2022 link
    • Traffic signals have been set at the intersection of Fort and 11th.
    • Concrete at Pueblo complete.
    • Water work will resume on Hays between 11th and 12th next year.
  • December 22, 2022

    Share December 22, 2022 on Facebook Share December 22, 2022 on Twitter Share December 22, 2022 on Linkedin Email December 22, 2022 link
    • Traffic signals have been set.
    • Concrete at Pueblo complete.
    • Water work will resume at Hays between 11th and 12th next year.
    • Power service is scheduled for December 26th at 11th and Franklin.
  • December 16, 2022

    Share December 16, 2022 on Facebook Share December 16, 2022 on Twitter Share December 16, 2022 on Linkedin Email December 16, 2022 link
    • Traffic signals have been set.
    • Prep work has started for ped ramps at Pueblo - waiting on concrete.
    • Water work will resume on Hays between 11th and 12th next year.
    • Power service is scheduled for December 20th at 11th and Franklin.
  • December 9, 2022

    Share December 9, 2022 on Facebook Share December 9, 2022 on Twitter Share December 9, 2022 on Linkedin Email December 9, 2022 link
    • Traffic signals have been set.
    • Prep work has started for ped ramps at Pueblo - waiting on concrete.
    • Water work will resume on Hays between 11th and 12th next year.
    • Power service is scheduled for December 20th at 11th and Franklin.
  • December 2, 2022

    Share December 2, 2022 on Facebook Share December 2, 2022 on Twitter Share December 2, 2022 on Linkedin Email December 2, 2022 link
    • Waiting on signals to be set.
    • Prep work has started for ped ramps at Pueblo.
    • Water work will resume on Hays between 11th and 12th.
  • November 23, 2022

    Share November 23, 2022 on Facebook Share November 23, 2022 on Twitter Share November 23, 2022 on Linkedin Email November 23, 2022 link
    • Intersection has been reopened to traffic.
    • Waiting on signals to be set.
    • Prep work has started for ped ramps at Pueblo.
    • Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
  • November 18, 2022

    Share November 18, 2022 on Facebook Share November 18, 2022 on Twitter Share November 18, 2022 on Linkedin Email November 18, 2022 link
    • The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
    • Contractor started back up on October 3rd at the intersection of Fort and 11th.
    • Intersection has been paved back and three of the four corners have been placed.
    • Waiting on signals to be set.
    • Paving mainline from Fort to O'Farrell St. - Complete.
    • Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
  • November 10, 2022

    Share November 10, 2022 on Facebook Share November 10, 2022 on Twitter Share November 10, 2022 on Linkedin Email November 10, 2022 link
    • The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
    • Contractor started back up on October 3rd at the intersection of Fort and 11th.
    • All four corners are demoed.
    • Concrete formwork set in preparation for concrete.
    • Paving mainline from Fort to O'Farrell St. - November 8th.
    • Water work will resume on Hays between 11th and 12th once the work on Fort is complete.
  • November 4, 2022

    Share November 4, 2022 on Facebook Share November 4, 2022 on Twitter Share November 4, 2022 on Linkedin Email November 4, 2022 link
    • The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
    • Contractor started back up on October 3rd at the intersection of Fort and 11th.
    • Concrete formwork set in preparation for concrete.
    • 3 of the 4 corners have been placed.
    • Paving mainline from Fort to Ofarell, Wednesday November 9th - pending weather.
    • Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.