-
Share May 10, 2024 on Facebook
Share May 10, 2024 on X (formerly Twitter)
Share May 10, 2024 on Linkedin
Email May 10, 2024 link
- State Street, 2nd Street to east of 4th Street - Complete.
- State Street/16th Street intersection - Electrical contractor is complete with underground. Waiting for fiber swap. Pole bases have been placed.
- State Street, 2nd Street to east of 4th Street - Complete.
- State Street/16th Street intersection - Electrical contractor is complete with underground. Waiting for fiber swap. Pole bases have been placed.
This project is substantially complete.
-
Share May 3, 2024 on Facebook
Share May 3, 2024 on X (formerly Twitter)
Share May 3, 2024 on Linkedin
Email May 3, 2024 link
- State Street/16th Street intersection - Electrical contractor is nearly complete with underground.
- Fiber work ongoing.
- Pole bases have been placed.
- State Street/16th Street intersection - Electrical contractor is nearly complete with underground.
- Fiber work ongoing.
- Pole bases have been placed.
This project is substantially complete.
-
Share April 25, 2024 on Facebook
Share April 25, 2024 on X (formerly Twitter)
Share April 25, 2024 on Linkedin
Email April 25, 2024 link
- State Street, 2nd Street to east of 4th Street - Complete.
- State Street/16th Street intersection - Road closures and lane restrictions have started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has complete on both the north and south side of State Street.
- Electrical contractor is nearly complete with underground.
- State Street, 2nd Street to east of 4th Street - Complete.
- State Street/16th Street intersection - Road closures and lane restrictions have started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has complete on both the north and south side of State Street.
- Electrical contractor is nearly complete with underground.
This project is substantially complete.
-
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Road closures and lane restrictions have started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has started on both the north and south side of State Street.
- Electrical contractor is nearly complete with underground.
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Road closures and lane restrictions have started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has started on both the north and south side of State Street.
- Electrical contractor is nearly complete with underground.
This project is substantially complete.
-
Share April 12, 2024 on Facebook
Share April 12, 2024 on X (formerly Twitter)
Share April 12, 2024 on Linkedin
Email April 12, 2024 link
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Bore complete across State Street for electrical. Road closures and lane restrictions have started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has started on both the north and south side of State Street.
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Bore complete across State Street for electrical. Road closures and lane restrictions have started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has started on both the north and south side of State Street.
This project is substantially complete.
-
Share April 5, 2024 on Facebook
Share April 5, 2024 on X (formerly Twitter)
Share April 5, 2024 on Linkedin
Email April 5, 2024 link
- State Street, 2nd Street to east of 4th Street
- Waiting on bioretention beds to be completed
- State Street/16th Street intersection
- Bore complete across State Street for electrical.
- Road closures and lane restrictions has started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has started on both the north and south side of State Street
- State Street, 2nd Street to east of 4th Street
- Waiting on bioretention beds to be completed
- State Street/16th Street intersection
- Bore complete across State Street for electrical.
- Road closures and lane restrictions has started.
- 16th Street is closed.
- State Street is reduced to one lane in each direction.
- Demo has started on both the north and south side of State Street
This project is substantially complete.
-
Share March 29, 2024 on Facebook
Share March 29, 2024 on X (formerly Twitter)
Share March 29, 2024 on Linkedin
Email March 29, 2024 link
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Planning to bore for electrical March 28th across State St.
- Road closures and lane restrictions are scheduled for the first week in April.
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Planning to bore for electrical March 28th across State St.
- Road closures and lane restrictions are scheduled for the first week in April.
This project is substantially complete.
-
Share March 30, 2024 - Detour Map Information on Facebook
Share March 30, 2024 - Detour Map Information on X (formerly Twitter)
Share March 30, 2024 - Detour Map Information on Linkedin
Email March 30, 2024 - Detour Map Information link
Please see the detour map for the construction project for State Street & 16th Street.
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Planning to bore for electrical March 28th across State St. This will be night work. Road closures and lane restrictions are scheduled for the first week in April.

Please see the detour map for the construction project for State Street & 16th Street.
- State Street, 2nd Street to east of 4th Street - Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Planning to bore for electrical March 28th across State St. This will be night work. Road closures and lane restrictions are scheduled for the first week in April.

This project is substantially complete.
-
Share March 15, 2024 on Facebook
Share March 15, 2024 on X (formerly Twitter)
Share March 15, 2024 on Linkedin
Email March 15, 2024 link
- State Street, 2nd Street to east of 4th Street - Concrete complete. Landscape repair complete. Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Planning to bore for electrical March 28th across State St. This will be night work.
- State Street, 2nd Street to east of 4th Street - Concrete complete. Landscape repair complete. Waiting on bioretention beds to be completed.
- State Street/16th Street intersection - Planning to bore for electrical March 28th across State St. This will be night work.
This project is substantially complete.
-
Share March 8, 2024 on Facebook
Share March 8, 2024 on X (formerly Twitter)
Share March 8, 2024 on Linkedin
Email March 8, 2024 link
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair complete.
- State Street/16th Street intersection - Planning to boring for electrical next week.
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair complete.
- State Street/16th Street intersection - Planning to boring for electrical next week.
This project is substantially complete.