-
Share January 19, 2024 on Facebook
Share January 19, 2024 on X (formerly Twitter)
Share January 19, 2024 on Linkedin
Email January 19, 2024 link
- Road closed for the duration of the work.
- Lumen Relocated utilities.
- Contractor removing asphalt.
- Placed culvert.
- Waiting for better weather for concrete.
- Road closed for the duration of the work.
- Lumen Relocated utilities.
- Contractor removing asphalt.
- Placed culvert.
- Waiting for better weather for concrete.
This project is substantially complete.
-
Share January 12, 2024 on Facebook
Share January 12, 2024 on X (formerly Twitter)
Share January 12, 2024 on Linkedin
Email January 12, 2024 link
- Road closed for the duration of the work.
- Lumen relocated utilities.
- Contractor removing asphalt.
- Placed culvert.
- Setting forms for concrete
- Road closed for the duration of the work.
- Lumen relocated utilities.
- Contractor removing asphalt.
- Placed culvert.
- Setting forms for concrete
This project is substantially complete.
-
Share January 5, 2024 on Facebook
Share January 5, 2024 on X (formerly Twitter)
Share January 5, 2024 on Linkedin
Email January 5, 2024 link
- Road closed for the duration of the work
- Lumen relocated utilities
- Contractor removing asphalt
- Placed culvert
- Setting forms for concrete
- Road closed for the duration of the work
- Lumen relocated utilities
- Contractor removing asphalt
- Placed culvert
- Setting forms for concrete
This project is substantially complete.
-
Share December 22, 2023 on Facebook
Share December 22, 2023 on X (formerly Twitter)
Share December 22, 2023 on Linkedin
Email December 22, 2023 link
- Road closed for the duration of the work.
- Lumen Relocated utilities.
- Contractor removing asphalt.
- Removing existing culvert.
- Veolia relocating water line.
- Road closed for the duration of the work.
- Lumen Relocated utilities.
- Contractor removing asphalt.
- Removing existing culvert.
- Veolia relocating water line.
This project is substantially complete.
-
Share December 15, 2023 on Facebook
Share December 15, 2023 on X (formerly Twitter)
Share December 15, 2023 on Linkedin
Email December 15, 2023 link
- Road closed for the duration of the work.
- Lumen Relocated utilities.
- Contractor removing asphalt.
- Removing existing culvert.
- Road closed for the duration of the work.
- Lumen Relocated utilities.
- Contractor removing asphalt.
- Removing existing culvert.
This project is substantially complete.
-
Share December 8, 2023 on Facebook
Share December 8, 2023 on X (formerly Twitter)
Share December 8, 2023 on Linkedin
Email December 8, 2023 link
- Road closed for the duration of the work.
- Waiting for Lumen to relocate utilities.
- Road closed for the duration of the work.
- Waiting for Lumen to relocate utilities.
This project is substantially complete.
-
Share December 1, 2023 on Facebook
Share December 1, 2023 on X (formerly Twitter)
Share December 1, 2023 on Linkedin
Email December 1, 2023 link
- Road closed for the duration of the work.
- Waiting for Lumen to relocate utilities.
- Road closed for the duration of the work.
- Waiting for Lumen to relocate utilities.
This project is substantially complete.
-
Share November 22, 2023 on Facebook
Share November 22, 2023 on X (formerly Twitter)
Share November 22, 2023 on Linkedin
Email November 22, 2023 link
- Waiting for Lumen to relocate utilities.
- Waiting for Lumen to relocate utilities.
This project is substantially complete.
-
Share November 17, 2023 on Facebook
Share November 17, 2023 on X (formerly Twitter)
Share November 17, 2023 on Linkedin
Email November 17, 2023 link
Waiting for Lumen to relocate utilities
Waiting for Lumen to relocate utilities
This project is substantially complete.
-
Share November 9, 2023 on Facebook
Share November 9, 2023 on X (formerly Twitter)
Share November 9, 2023 on Linkedin
Email November 9, 2023 link
- Waiting for Lumen to relocate utilities.
- Waiting for Lumen to relocate utilities.
This project is substantially complete.