37th Street Bridge
Work substantially complete.
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on 37th Street, southwest of Adams Street, as early as the beginning of October 2023 .* Construction is expected to be complete spring of 2024.
This bridge improvement project will include removing and replacing the existing bridge over the Boise City Canal.
*Construction schedules may change due to high demand for contractors, labor, and supplies.
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on 37th Street, southwest of Adams Street, as early as the beginning of October 2023 .* Construction is expected to be complete spring of 2024.
This bridge improvement project will include removing and replacing the existing bridge over the Boise City Canal.
*Construction schedules may change due to high demand for contractors, labor, and supplies.
Work substantially complete.
-
May 10, 2024
Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 linkWork substantially complete.
Work substantially complete.
Work substantially complete.
-
April 25, 2024
Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link- Asphalt paving was completed on April 18th.
- Landscape repair work started.
- Minor items remain.
- Asphalt paving was completed on April 18th.
- Landscape repair work started.
- Minor items remain.
Work substantially complete.
-
April 19, 2024
Share April 19, 2024 on Facebook Share April 19, 2024 on Twitter Share April 19, 2024 on Linkedin Email April 19, 2024 link- Sewer work for Garden City complete within project limits.
- Road base prep is complete.
- Asphalt paving was completed on April 18th.
- Sewer work for Garden City complete within project limits.
- Road base prep is complete.
- Asphalt paving was completed on April 18th.
Work substantially complete.
-
April 12, 2024
Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link- Sewer work for Garden City started April 1st.
- Road base prep has started.
- Contractor anticipates paving the week of April 15th.
- Sewer work for Garden City started April 1st.
- Road base prep has started.
- Contractor anticipates paving the week of April 15th.
Work substantially complete.
-
April 5, 2024
Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link- Sewer work for Garden City started April 1st.
- Road base prep has started.
- Contractor anticipates paving on the 15th of April.
- Sewer work for Garden City started April 1st.
- Road base prep has started.
- Contractor anticipates paving on the 15th of April.
Work substantially complete.
-
March 29, 2024
Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link- Sewer work for Garden City will start April 1st.
- Road base prep has started.
- Sewer work for Garden City will start April 1st.
- Road base prep has started.
Work substantially complete.
-
March 21, 2024
Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link- Sewer work for Garden City will start April 1st.
- Grate and trash rack installed.
- Sewer work for Garden City will start April 1st.
- Grate and trash rack installed.
Work substantially complete.
-
March 15, 2024
Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link- Sewer work for Garden City will start in late March/early April.
- Curb & gutter work complete.
- Sidewalk placements on-going.
- Grate and trash rack will be installed this week.
- Sewer work for Garden City will start in late March/early April.
- Curb & gutter work complete.
- Sidewalk placements on-going.
- Grate and trash rack will be installed this week.
Work substantially complete.
-
March 8, 2024
Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link- Sewer work for Garden City will start in late March.
- Curb & gutter work complete.
- Sidewalk placements on-going.
- Grate and trash rack in stall this week.
- Sewer work for Garden City will start in late March.
- Curb & gutter work complete.
- Sidewalk placements on-going.
- Grate and trash rack in stall this week.
Work substantially complete.
-
March 1, 2024
Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link- Sewer work for Garden City will start the first week of March.
- Curb & gutter work complete.
- Sidewalk placements on-going.
- Sewer work for Garden City will start the first week of March.
- Curb & gutter work complete.
- Sidewalk placements on-going.
Work substantially complete.