37th Street Bridge

Share 37th Street Bridge on Facebook Share 37th Street Bridge on Twitter Share 37th Street Bridge on Linkedin Email 37th Street Bridge link

Work substantially complete. 

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on 37th Street, southwest of Adams Street, as early as the beginning of October 2023 .* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Boise City Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on 37th Street, southwest of Adams Street, as early as the beginning of October 2023 .* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Boise City Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

Work substantially complete. 

  • December 8, 2023

    Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link
    • Utility work started November 15th.
    • Bridge/Culvert demo started.
    • Notification boards have been set.
    • 37th Street will be closed for the duration of the work.
    • Coordination with Garden City sewer work continues.
  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link
    • Utility work started November 15th.
    • Bridge work will begin the first week of December.
    • Notification boards have been set. 37th Street will be closed for the duration of the work.
  • November 22, 2023

    Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link
    • Utility work started November 15th .
    • Bridge work will begin the first week of December.
  • November 17, 2023

    Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link

    o Utility work started November 15th

    o Bridge work will begin the first week of December

  • November 9, 2023

    Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link
    • Utility work is scheduled to start the week of November 27th.
    • Bridge work will begin later this winter.
  • August 24, 2023

    Share August 24, 2023 on Facebook Share August 24, 2023 on Twitter Share August 24, 2023 on Linkedin Email August 24, 2023 link

    ACHD will begin reconstructing the culvert on 37th Street this fall.

    Construction Impacts

    • Temporary road closures
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize construction impacts
  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • This project is on hold until the Fall.