Carlsbad Way Bridge

Share Carlsbad Way Bridge on Facebook Share Carlsbad Way Bridge on Twitter Share Carlsbad Way Bridge on Linkedin Email Carlsbad Way Bridge link

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Carlsbad Way, just north of State Street, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Boise Valley Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Carlsbad Way, just north of State Street, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Boise Valley Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Roadway is closed for the duration of the work.
    • City of Boise Sewer line in conflict; relocated.
    • Water line relocation complete.
    • Concrete work ongoing.
  • January 26, 2026

    Share January 26, 2026 on Facebook Share January 26, 2026 on Twitter Share January 26, 2026 on Linkedin Email January 26, 2026 link
    • Roadway is closed for the duration of the work.
    • City of Boise Sewer line in conflict; relocated.
    • Concrete work ongoing.
  • January 19, 2024

    Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link
    • Roadway is closed for the duration of the work.
    • City of Boise Sewer line in conflict; relocated.
    • Concrete work ongoing.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Roadway is closed for the duration of the work.
    • City of Boise Sewer line in conflict; working on relocating.
    • Concrete work ongoing.
  • January 5, 2024

    Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link
    • Roadway is closed for the duration of the work.
    • City of Boise Sewer line in conflict; working on relocating.
    • Placing culvert pieces.
    • Setting forms for closure pours.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Roadway is closed for the duration of the work.
    • City of Boise Sewer line in conflict working on relocating.
    • Placing culvert pieces.
  • December 15, 2023

    Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link
    • Roadway is closed for the duration of the work.
    • Contractor removing culvert.
    • City of Boise Sewer line in conflict working on relocating.
    • Placing culvert pieces.
  • December 8, 2023

    Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link
    • Roadway is closed for the duration of the work.
    • Contractor removing culvert.
    • Precast components being constructed.
    • Granite Excavation relocating water line.
  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link
    • Roadway is closed for the duration of the work.
    • Contractor removing culvert.
    • Precast components being constructed.
    • Granite Excavation relocating water line.
  • November 22, 2023

    Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link
    • Roadway is closed for the duration of the work.
    • Contractor removing culvert.
    • Precast components being constructed.
    • Granite Construction relocating water line.
Page last updated: 12 Apr 2024, 02:26 PM