Chateau Drive Construction

Share Chateau Drive Construction on Facebook Share Chateau Drive Construction on Twitter Share Chateau Drive Construction on Linkedin Email Chateau Drive Construction link

This project is substantially complete. 

The Ada County Highway District (ACHD) will begin construction on Chateau Drive, near Barbara Morgan STEM Academy, in late June. Construction is expected to be completed in late summer of 2024.*

The project involves three main components: replacing the pedestrian ramps at the school entrance, realigning the existing crosswalk, and installing a seepage bed. The purpose of this project is to improve pedestrian accessibility and drainage in the area.

Construction Impacts

  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

*Due to high demand for contractors, labor and supplies, the construction schedules may change.

The Ada County Highway District (ACHD) will begin construction on Chateau Drive, near Barbara Morgan STEM Academy, in late June. Construction is expected to be completed in late summer of 2024.*

The project involves three main components: replacing the pedestrian ramps at the school entrance, realigning the existing crosswalk, and installing a seepage bed. The purpose of this project is to improve pedestrian accessibility and drainage in the area.

Construction Impacts

  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

*Due to high demand for contractors, labor and supplies, the construction schedules may change.

This project is substantially complete. 

  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • Pipe and seepage bed complete.
    • Curb concrete complete.
    • Sidewalk concrete placement this week.
    • Paving and lane lines scheduled for late this week, or early next week.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link

    The preconstruction meeting is scheduled for June 12th.