-
Share October 6, 2023 on Facebook
Share October 6, 2023 on X (formerly Twitter)
Share October 6, 2023 on Linkedin
Email October 6, 2023 link
- Concrete placements for curb, gutter and sidewalk are complete.
- Northbound lane is complete.
- Work on southbound lane started September 13th and is ongoing. Asphalt paving is scheduled to be complete on October 6th.
- Concrete placements for curb, gutter and sidewalk are complete.
- Northbound lane is complete.
- Work on southbound lane started September 13th and is ongoing. Asphalt paving is scheduled to be complete on October 6th.
-
Share September 29, 2023 on Facebook
Share September 29, 2023 on X (formerly Twitter)
Share September 29, 2023 on Linkedin
Email September 29, 2023 link
- Concrete placements for curb, gutter and sidewalk are complete.
- Asphalt paving of the northbound lanes was completed September 12th.
- Work on the southbound lanes started September 13th - ongoing.
- Concrete placements for curb, gutter and sidewalk are complete.
- Asphalt paving of the northbound lanes was completed September 12th.
- Work on the southbound lanes started September 13th - ongoing.
-
Share September 22, 2023 on Facebook
Share September 22, 2023 on X (formerly Twitter)
Share September 22, 2023 on Linkedin
Email September 22, 2023 link
- Concrete placements for curb, gutter and sidewalk are complete.
- Asphalt paving of the northbound lanes was completed September 12th.
- Work on the southbound lanes started September 13th and is ongoing.
- Concrete placements for curb, gutter and sidewalk are complete.
- Asphalt paving of the northbound lanes was completed September 12th.
- Work on the southbound lanes started September 13th and is ongoing.
-
Share September 15, 2023 on Facebook
Share September 15, 2023 on X (formerly Twitter)
Share September 15, 2023 on Linkedin
Email September 15, 2023 link
- Concrete placements for curb, gutter and sidewalk are complete.
- Asphalt paving of the northbound lanes was completed September 12th.
- work on the southbound lanes started September 13th.
- Concrete placements for curb, gutter and sidewalk are complete.
- Asphalt paving of the northbound lanes was completed September 12th.
- work on the southbound lanes started September 13th.
-
Share September 8, 2023 on Facebook
Share September 8, 2023 on X (formerly Twitter)
Share September 8, 2023 on Linkedin
Email September 8, 2023 link
- Concrete placements for curb, gutter, & sidewalk are complete.
- Contractor is removing existing concrete pavement in the northbound lanes.
- Asphalt paving of the northbound lanes is scheduled for the week of September 11th.
- Concrete placements for curb, gutter, & sidewalk are complete.
- Contractor is removing existing concrete pavement in the northbound lanes.
- Asphalt paving of the northbound lanes is scheduled for the week of September 11th.
-
Share August 25, 2023 on Facebook
Share August 25, 2023 on X (formerly Twitter)
Share August 25, 2023 on Linkedin
Email August 25, 2023 link
- The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
- Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing through the end of the month.
- Contractor is removing existing concrete pavement in the northbound lanes.
- The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
- Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing through the end of the month.
- Contractor is removing existing concrete pavement in the northbound lanes.
-
Share August 18, 2023 on Facebook
Share August 18, 2023 on X (formerly Twitter)
Share August 18, 2023 on Linkedin
Email August 18, 2023 link
- The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
- Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing.
- The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
- Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing.
-
Share August 11, 2023 on Facebook
Share August 11, 2023 on X (formerly Twitter)
Share August 11, 2023 on Linkedin
Email August 11, 2023 link
- The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
- Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing.
- The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
- Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing.
-
Share August 4, 2023 on Facebook
Share August 4, 2023 on X (formerly Twitter)
Share August 4, 2023 on Linkedin
Email August 4, 2023 link
- Crews excavating for sidewalk removal and prepping for sidewalk replacement.
- Concrete placements for curb and gutter began August 3rd.
- Crews excavating for sidewalk removal and prepping for sidewalk replacement.
- Concrete placements for curb and gutter began August 3rd.
-
Share July 28, 2023 on Facebook
Share July 28, 2023 on X (formerly Twitter)
Share July 28, 2023 on Linkedin
Email July 28, 2023 link
- Work started on July 17th.
- Crews sawcutting concrete pavement for sidewalk removal and replacement.
- Work started on July 17th.
- Crews sawcutting concrete pavement for sidewalk removal and replacement.