Collister Drive Maintenance and Pedestrian Project, Quail Ridge Dr. to the cul-de-sac to the north

Share Collister Drive Maintenance and Pedestrian Project, Quail Ridge Dr. to the cul-de-sac to the north on Facebook Share Collister Drive Maintenance and Pedestrian Project, Quail Ridge Dr. to the cul-de-sac to the north on Twitter Share Collister Drive Maintenance and Pedestrian Project, Quail Ridge Dr. to the cul-de-sac to the north on Linkedin Email Collister Drive Maintenance and Pedestrian Project, Quail Ridge Dr. to the cul-de-sac to the north link

Project Description

  • Remove existing, deteriorating concrete roadway and replace with asphalt.
  • Add speed humps.
  • Replace the existing curb, gutter and four-foot sidewalk on the east side of the street with rolled curb and a five-foot sidewalk, matching the existing back of sidewalk.
  • The intent is to have minimal impacts to private property; therefore, the new sidewalk will match the back of the existing sidewalk. However, temporary easements will still be needed during construction to facilitate sod repairs and sprinkler work.
  • Temporary easements will allow for a working area and access as required for any driveway repairs, sprinkler/sod repairs, or other minor repair work that may be required on private properties for the installation of the new sidewalk.

Project Purpose

  • Improve roadway surface
  • Update pedestrian facilities to modern standards

Project Considerations

  • Safety for pedestrians, bicyclists and motorists
  • Property impacts
  • Pavement condition
  • Accessible sidewalks and pedestrian ramps

Project Description

  • Remove existing, deteriorating concrete roadway and replace with asphalt.
  • Add speed humps.
  • Replace the existing curb, gutter and four-foot sidewalk on the east side of the street with rolled curb and a five-foot sidewalk, matching the existing back of sidewalk.
  • The intent is to have minimal impacts to private property; therefore, the new sidewalk will match the back of the existing sidewalk. However, temporary easements will still be needed during construction to facilitate sod repairs and sprinkler work.
  • Temporary easements will allow for a working area and access as required for any driveway repairs, sprinkler/sod repairs, or other minor repair work that may be required on private properties for the installation of the new sidewalk.

Project Purpose

  • Improve roadway surface
  • Update pedestrian facilities to modern standards

Project Considerations

  • Safety for pedestrians, bicyclists and motorists
  • Property impacts
  • Pavement condition
  • Accessible sidewalks and pedestrian ramps
  • October 6, 2023

    Share October 6, 2023 on Facebook Share October 6, 2023 on Twitter Share October 6, 2023 on Linkedin Email October 6, 2023 link
    • Concrete placements for curb, gutter and sidewalk are complete.
    • Northbound lane is complete.
    • Work on southbound lane started September 13th and is ongoing. Asphalt paving is scheduled to be complete on October 6th.
  • September 29, 2023

    Share September 29, 2023 on Facebook Share September 29, 2023 on Twitter Share September 29, 2023 on Linkedin Email September 29, 2023 link
    • Concrete placements for curb, gutter and sidewalk are complete.
    • Asphalt paving of the northbound lanes was completed September 12th.
    • Work on the southbound lanes started September 13th - ongoing.
  • September 22, 2023

    Share September 22, 2023 on Facebook Share September 22, 2023 on Twitter Share September 22, 2023 on Linkedin Email September 22, 2023 link
    • Concrete placements for curb, gutter and sidewalk are complete.
    • Asphalt paving of the northbound lanes was completed September 12th.
    • Work on the southbound lanes started September 13th and is ongoing.
  • September 15, 2023

    Share September 15, 2023 on Facebook Share September 15, 2023 on Twitter Share September 15, 2023 on Linkedin Email September 15, 2023 link
    • Concrete placements for curb, gutter and sidewalk are complete.
    • Asphalt paving of the northbound lanes was completed September 12th.
    • work on the southbound lanes started September 13th.
  • September 8, 2023

    Share September 8, 2023 on Facebook Share September 8, 2023 on Twitter Share September 8, 2023 on Linkedin Email September 8, 2023 link
    • Concrete placements for curb, gutter, & sidewalk are complete.
    • Contractor is removing existing concrete pavement in the northbound lanes.
    • Asphalt paving of the northbound lanes is scheduled for the week of September 11th.
  • August 25, 2023

    Share August 25, 2023 on Facebook Share August 25, 2023 on Twitter Share August 25, 2023 on Linkedin Email August 25, 2023 link
    • The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
    • Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing through the end of the month.
    • Contractor is removing existing concrete pavement in the northbound lanes.
  • August 18, 2023

    Share August 18, 2023 on Facebook Share August 18, 2023 on Twitter Share August 18, 2023 on Linkedin Email August 18, 2023 link
    • The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
    • Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing.
  • August 11, 2023

    Share August 11, 2023 on Facebook Share August 11, 2023 on Twitter Share August 11, 2023 on Linkedin Email August 11, 2023 link
    • The existing sidewalk has been removed. Crews prepping grade for sidewalk replacement.
    • Concrete placements for curb, gutter and sidewalk began August 3rd and are ongoing.
  • August 4, 2023

    Share August 4, 2023 on Facebook Share August 4, 2023 on Twitter Share August 4, 2023 on Linkedin Email August 4, 2023 link
    • Crews excavating for sidewalk removal and prepping for sidewalk replacement.
    • Concrete placements for curb and gutter began August 3rd.
  • July 28, 2023

    Share July 28, 2023 on Facebook Share July 28, 2023 on Twitter Share July 28, 2023 on Linkedin Email July 28, 2023 link
    • Work started on July 17th.
    • Crews sawcutting concrete pavement for sidewalk removal and replacement.
Page last updated: 06 Oct 2023, 03:49 PM