Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt

Share Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt on Facebook Share Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt on Twitter Share Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt on Linkedin Email Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt link

This project is substantially complete.

The Ada County Highway District (ACHD) is designing sidewalks for Garden Street between Albion Street and Emerald Street, as well as a bikeway between Albion Street and the Greenbelt. The purpose of this project is to improve safety and increase connectivity for pedestrians and bicyclists. This project now includes Garden Street, Franklin Road to Bethel Street that was designed in 2019.

Project Description

Sidewalk

  • Add curb, gutter, and sidewalk on both sides of Garden Street, Albion Street to Emerald Street; Reconstruct some existing sidewalk as necessary.
  • Improve pedestrian ramps.
  • Add bulb-outs at key locations.

Bikeway

  • Add lane markings & wayfinding signage to create a bikeway on Garden Street between Albion Street and the Greenbelt.
  • Improve alignment of the Garden Street and Franklin Street intersection and add an enhanced pedestrian/bike signal.

Roadway

  • Reconstruct the roadway.
  • Replace pipes and the bridge north of Mason Drive.
  • Upgrade existing speed humps to "speed cushions", which will ease emergency vehicle access.
  • Utility work.
  • Most on-street parking will be retained however, some parking will be impacted.

Purpose

  • Increase connectivity for pedestrians
  • Improve quality of the street

Background

This project was one of several identified in the 2012 Boise Central Bench Neighborhood Bicycle and Pedestrian Plan as a priority for sidewalk completion.


The Ada County Highway District (ACHD) is designing sidewalks for Garden Street between Albion Street and Emerald Street, as well as a bikeway between Albion Street and the Greenbelt. The purpose of this project is to improve safety and increase connectivity for pedestrians and bicyclists. This project now includes Garden Street, Franklin Road to Bethel Street that was designed in 2019.

Project Description

Sidewalk

  • Add curb, gutter, and sidewalk on both sides of Garden Street, Albion Street to Emerald Street; Reconstruct some existing sidewalk as necessary.
  • Improve pedestrian ramps.
  • Add bulb-outs at key locations.

Bikeway

  • Add lane markings & wayfinding signage to create a bikeway on Garden Street between Albion Street and the Greenbelt.
  • Improve alignment of the Garden Street and Franklin Street intersection and add an enhanced pedestrian/bike signal.

Roadway

  • Reconstruct the roadway.
  • Replace pipes and the bridge north of Mason Drive.
  • Upgrade existing speed humps to "speed cushions", which will ease emergency vehicle access.
  • Utility work.
  • Most on-street parking will be retained however, some parking will be impacted.

Purpose

  • Increase connectivity for pedestrians
  • Improve quality of the street

Background

This project was one of several identified in the 2012 Boise Central Bench Neighborhood Bicycle and Pedestrian Plan as a priority for sidewalk completion.


This project is substantially complete.

  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Bethel to Morris Hill - Placing culvert walls February 8th.
    • Storm Drain and Irrigation work heading southbound.
    • Seepage bed at Bethel.
    • Veolia utility work Franklin and Alpine: Main line placed.
    • Boring anticipated February 28th.
    • Albion to Franklin o Installing irrigation lines and Storm Drain.
  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Bethel to Morris Hill - Placing culvert walls February 8th .
    • Storm Drain and Irrigation work heading southbound.
    • Seepage bed at Bethel.
    • Veolia utility work Franklin and Alpine: Main line placed. Boring anticipated February 28th.
    • Albion to Franklin - Installing irrigation lines and Storm Drain.
  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Bethel to Morris Hill - Placing culvert walls February 8th.
    • Storm Drain and Irrigation work heading southbound.
    • Seepage bed at Bethel.
    • Veolia utility work Franklin and Alpine: Main line placed. Boring anticipated February 28th.
  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
    • Contractor excavating and placing aggregate for box culvert.
    • Prepping for wingwalls.
    • Storm Drain and Irrigation work heading southbound.
    • Veolia utility work started at Albion: Main line placed to Rose Hill from Albion.
    • Boring at Rose Hill complete.
    • Services will be ongoing.
    • Air testing pipe.
  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
    • Contractor excavating and placing aggregate for box culvert.
    • Prepping for wingwalls.
    • Veolia utility work started at Albion: Main line placed to Rose Hill from Albion.
    • Boring at Rose Hill complete - Services will be ongoing.
    • Air Testing pipe.
  • January 19, 2024

    Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link
    • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
    • Contractor excavating and placing aggregate for box culvert.
    • Prepping for wingwalls.
    • Veolia utility work started at Albion - Main line placed to Rose Hill from Albion.
    • Boring at Rose Hill complete.
    • Services will be ongoing.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
    • Contractor excavating and placing aggregate for box culvert.
    • Prepping for wingwalls.
    • Veolia utility work started at Albion - Main line placed to Rose Hill from Albion.
    • Boring at Rose Hill complete.
    • Services will be ongoing
  • January 5, 2024

    Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link
    • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
    • Contractor excavating and placing aggregate for box culvert.
    • Culvert placed.
    • Prepping for Wingwalls.
    • Veolia utility work started at Albion.
    • Main line placed to Rose Hill from Albion.
    • Boring at Rose Hill complete.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Bethel to Morris Hill
      • Closure started November 27th for box culvert placement.
      • Contractor excavating and placing aggregate for box culvert.
      • Planning on setting structure December 20th.
    • Veolia utility work started at Albion
      • Garden Street closed between Albion and Franklin for duration of Veolia’s work.
  • December 15, 2023

    Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link
    • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
    • Contractor excavating and placing aggregate for box culvert.
    • Planning on setting structure December 20th.
    • Tree removal ongoing.
    • Veolia utility work started at Albion.