- Bethel to Morris Hill - Placing culvert walls February 8th.
- Storm Drain and Irrigation work heading southbound.
- Seepage bed at Bethel.
- Veolia utility work Franklin and Alpine: Main line placed.
- Boring anticipated February 28th.
- Albion to Franklin o Installing irrigation lines and Storm Drain.
Share February 16, 2024 on Facebook
Share February 16, 2024 on Linkedin
Email February 16, 2024 link
- Bethel to Morris Hill - Placing culvert walls February 8th .
- Storm Drain and Irrigation work heading southbound.
- Seepage bed at Bethel.
- Veolia utility work Franklin and Alpine: Main line placed. Boring anticipated February 28th.
- Albion to Franklin - Installing irrigation lines and Storm Drain.
Share February 9, 2024 on Facebook
Share February 9, 2024 on Linkedin
Email February 9, 2024 link
- Bethel to Morris Hill - Placing culvert walls February 8th.
- Storm Drain and Irrigation work heading southbound.
- Seepage bed at Bethel.
- Veolia utility work Franklin and Alpine: Main line placed. Boring anticipated February 28th.
Share February 2, 2024 on Facebook
Share February 2, 2024 on Linkedin
Email February 2, 2024 link
- Bethel to Morris Hill - Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Prepping for wingwalls.
- Storm Drain and Irrigation work heading southbound.
- Veolia utility work started at Albion: Main line placed to Rose Hill from Albion.
- Boring at Rose Hill complete.
- Services will be ongoing.
- Air testing pipe.
Share January 26, 2024 on Facebook
Share January 26, 2024 on Linkedin
Email January 26, 2024 link
- Bethel to Morris Hill - Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Prepping for wingwalls.
- Veolia utility work started at Albion: Main line placed to Rose Hill from Albion.
- Boring at Rose Hill complete - Services will be ongoing.
- Air Testing pipe.
Share January 19, 2024 on Facebook
Share January 19, 2024 on Linkedin
Email January 19, 2024 link
- Bethel to Morris Hill - Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Prepping for wingwalls.
- Veolia utility work started at Albion - Main line placed to Rose Hill from Albion.
- Boring at Rose Hill complete.
- Services will be ongoing.
Share January 12, 2024 on Facebook
Share January 12, 2024 on Linkedin
Email January 12, 2024 link
- Bethel to Morris Hill - Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Prepping for wingwalls.
- Veolia utility work started at Albion - Main line placed to Rose Hill from Albion.
- Boring at Rose Hill complete.
- Services will be ongoing
Share January 5, 2024 on Facebook
Share January 5, 2024 on Linkedin
Email January 5, 2024 link
- Bethel to Morris Hill - Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Culvert placed.
- Prepping for Wingwalls.
- Veolia utility work started at Albion.
- Main line placed to Rose Hill from Albion.
- Boring at Rose Hill complete.
Share December 22, 2023 on Facebook
Share December 22, 2023 on Linkedin
Email December 22, 2023 link
- Bethel to Morris Hill
- Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Planning on setting structure December 20th.
- Veolia utility work started at Albion
- Garden Street closed between Albion and Franklin for duration of Veolia’s work.
Share December 15, 2023 on Facebook
Share December 15, 2023 on Linkedin
Email December 15, 2023 link
- Bethel to Morris Hill - Closure started November 27th for box culvert placement.
- Contractor excavating and placing aggregate for box culvert.
- Planning on setting structure December 20th.
- Tree removal ongoing.
- Veolia utility work started at Albion.