Lake Hazel and Maple Grove Roundabout
This project is substantially complete.
The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.
Project Description
- Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
- Add curb, gutter, and a detached 10-foot wide multi-use pathway
- Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
- Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
- Add a truck apron for larger vehicles to use if necessary
The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.
Project Description
- Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
- Add curb, gutter, and a detached 10-foot wide multi-use pathway
- Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
- Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
- Add a truck apron for larger vehicles to use if necessary
This project is substantially complete.
-
July 12, 2024
Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link- All legs of the roundabout are open to traffic.
- Pedestrian railing on the southwest corner complete.
- All legs of the roundabout are open to traffic.
- Pedestrian railing on the southwest corner complete.
This project is substantially complete.
-
June 28, 2024
Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link- All legs of the roundabout are open to traffic.
- Minor work remains.
- Waiting on pedestrian railing on the southwest corner.
- All legs of the roundabout are open to traffic.
- Minor work remains.
- Waiting on pedestrian railing on the southwest corner.
This project is substantially complete.
-
June 21, 2024
Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link- All legs of the roundabout are open to traffic.
- Minor work remains.
- Waiting on pedestrian railing on the southwest corner.
- All legs of the roundabout are open to traffic.
- Minor work remains.
- Waiting on pedestrian railing on the southwest corner.
This project is substantially complete.
-
June 14, 2024
Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link- All legs of the roundabout are open to traffic.
- Minor work remains.
- Waiting on ped railing on the southwest corner.
- All legs of the roundabout are open to traffic.
- Minor work remains.
- Waiting on ped railing on the southwest corner.
This project is substantially complete.
-
June 7, 2024
Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link- All legs of the roundabout are open to traffic.
- Minor work remains.
- All legs of the roundabout are open to traffic.
- Minor work remains.
This project is substantially complete.
-
May 31, 2024
Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link- All legs of the roundabout are open to traffic.
- Minor work remains.
- All legs of the roundabout are open to traffic.
- Minor work remains.
This project is substantially complete.
-
May 23, 2024
Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link- South leg of roundabout scheduled to be open in late May or early June.
- Minor work remains.
- South leg of roundabout scheduled to be open in late May or early June.
- Minor work remains.
This project is substantially complete.
-
May 16, 2024
Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link- Contractor working on sidewalk at various locations around the project.
- Asphalt multiuse path complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
- Contractor working on sidewalk at various locations around the project.
- Asphalt multiuse path complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
This project is substantially complete.
-
May 10, 2024
Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
This project is substantially complete.
-
May 3, 2024
Share May 3, 2024 on Facebook Share May 3, 2024 on Twitter Share May 3, 2024 on Linkedin Email May 3, 2024 link- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete. Installation of pavement markings complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete. Installation of pavement markings complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
This project is substantially complete.
Who's Listening
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org