Lake Hazel and Maple Grove Roundabout

Share Lake Hazel and Maple Grove Roundabout on Facebook Share Lake Hazel and Maple Grove Roundabout on Twitter Share Lake Hazel and Maple Grove Roundabout on Linkedin Email Lake Hazel and Maple Grove Roundabout link

This project is substantially complete. 

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

This project is substantially complete. 

  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • All legs of the roundabout are open to traffic.
    • Pedestrian railing on the southwest corner complete.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • All legs of the roundabout are open to traffic.
    • Minor work remains.
    • Waiting on pedestrian railing on the southwest corner.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    • All legs of the roundabout are open to traffic.
    • Minor work remains.
    • Waiting on pedestrian railing on the southwest corner.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • All legs of the roundabout are open to traffic.
    • Minor work remains.
    • Waiting on ped railing on the southwest corner.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • All legs of the roundabout are open to traffic.
    • Minor work remains.
  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • All legs of the roundabout are open to traffic.
    • Minor work remains.
  • May 23, 2024

    Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link
    • South leg of roundabout scheduled to be open in late May or early June.
    • Minor work remains.
  • May 16, 2024

    Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Asphalt multiuse path complete.
    • Opened three legs of the roundabout April 26th.
    • South leg of roundabout scheduled to be open in late May or early June.
  • May 10, 2024

    Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Contractor completed concrete pavement mainline.
    • Asphalt paving complete.
    • Installation of pavement markings complete.
    • Opened three legs of the roundabout April 26th.
    • South leg of roundabout scheduled to be open in late May or early June.
  • May 3, 2024

    Share May 3, 2024 on Facebook Share May 3, 2024 on Twitter Share May 3, 2024 on Linkedin Email May 3, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Contractor completed concrete pavement mainline.
    • Asphalt paving complete. Installation of pavement markings complete.
    • Opened three legs of the roundabout April 26th.
    • South leg of roundabout scheduled to be open in late May or early June.