Liberty Street, Denton to Douglas
In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street between Denton Street and Douglas Street. The project includes pavement maintenance as well as safety and connectivity improvements for bicyclists and pedestrians. Work is expected to be complete in fall 2026.*
Project Description
- Perform pavement maintenance to improve roadway conditions on Liberty Street from Douglas to Denton.
- Construct curb, gutter, and a multi-use pathway on the east side of Liberty Street from Douglas to Denton.
- Add sidewalk on the west side of Liberty Street from Douglas to Denton.
- On-street parking will remain on the west side.
- Add new pedestrian ramps and bikeway signage where necessary.
Construction Impacts
- Road closures are expected during construction
- Traffic lanes will shift as work progresses
- On-street parking will be reduced during construction
- Lane restrictions with flaggers will help direct traffic
- Expect general construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
*Construction schedules may change.
In November, the Ada County Highway District (ACHD) will begin construction on Liberty Street between Denton Street and Douglas Street. The project includes pavement maintenance as well as safety and connectivity improvements for bicyclists and pedestrians. Work is expected to be complete in fall 2026.*
Project Description
- Perform pavement maintenance to improve roadway conditions on Liberty Street from Douglas to Denton.
- Construct curb, gutter, and a multi-use pathway on the east side of Liberty Street from Douglas to Denton.
- Add sidewalk on the west side of Liberty Street from Douglas to Denton.
- On-street parking will remain on the west side.
- Add new pedestrian ramps and bikeway signage where necessary.
Construction Impacts
- Road closures are expected during construction
- Traffic lanes will shift as work progresses
- On-street parking will be reduced during construction
- Lane restrictions with flaggers will help direct traffic
- Expect general construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
*Construction schedules may change.
-
October 2, 2026
Share October 2, 2026 on Facebook Share October 2, 2026 on X (formerly Twitter) Share October 2, 2026 on Linkedin Email October 2, 2026 link- Liberty Street is closed to southbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Utility work is complete.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
- Liberty Street is closed to southbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Utility work is complete.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
-
September 24, 2026
Share September 24, 2026 on Facebook Share September 24, 2026 on X (formerly Twitter) Share September 24, 2026 on Linkedin Email September 24, 2026 link- Liberty Street is closed to southbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Utility work is complete.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
- Liberty Street is closed to southbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Utility work is complete.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
-
September 17, 2026
Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 link- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
-
September 11, 2026
Share September 11, 2026 on Facebook Share September 11, 2026 on X (formerly Twitter) Share September 11, 2026 on Linkedin Email September 11, 2026 link- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd.
- Work is on-going and anticipated to be complete the week of September 7th.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd.
- Work is on-going and anticipated to be complete the week of September 7th.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
-
September 3, 2026
Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 link- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete the week of September 7th.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5 th. Work is on-going.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete the week of September 7th.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5 th. Work is on-going.
-
August 28, 2026
Share August 28, 2026 on Facebook Share August 28, 2026 on X (formerly Twitter) Share August 28, 2026 on Linkedin Email August 28, 2026 link- Liberty Street is closed to southbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th
- Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete the week of August 31st.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
- Liberty Street is closed to southbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th
- Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete the week of August 31st.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th. Work is on-going.
-
August 20, 2026
Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 link- Liberty Street is closed to southbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd.
- Work is on-going and anticipated to be complete at the end of August.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th.
- Liberty Street is closed to southbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd.
- Work is on-going and anticipated to be complete at the end of August.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th.
-
August 14, 2026
Share August 14, 2026 on Facebook Share August 14, 2026 on X (formerly Twitter) Share August 14, 2026 on Linkedin Email August 14, 2026 link- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete at the end of August.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going and anticipated to be complete at the end of August.
- ACHD’s contractor started roadway and sidewalk work for Phase 2 on August 5th.
-
August 7, 2026
Share August 7, 2026 on Facebook Share August 7, 2026 on X (formerly Twitter) Share August 7, 2026 on Linkedin Email August 7, 2026 link- Liberty Street is closed to southbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road
- and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th
- Work on the west side of the roadway began on June 19th
- Veolia began replacing the water line on June 23rd. Work is on-going
- ACHD’s contractor anticipates starting roadway and sidewalk work for Phase 2 on August 10th
- Liberty Street is closed to southbound traffic between Franklin Road. and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road
- and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th
- Work on the west side of the roadway began on June 19th
- Veolia began replacing the water line on June 23rd. Work is on-going
- ACHD’s contractor anticipates starting roadway and sidewalk work for Phase 2 on August 10th
-
July 30, 2026
Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 link- Liberty Street is closed to southbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going.
- ACHD’s contractor anticipates starting roadway and sidewalk work for Phase 2 on August 10th.
- Liberty Street is closed to southbound traffic between Franklin Road and Denton Street.
- Liberty Street is open to one-lane, one-way traffic in the northbound direction between Franklin Road and Denton Street.
- Concrete for curb & gutter and sidewalk on the east side started May 7th and is on-going.
- Asphalt paving for Phase 1 on the east side was completed on June 5th.
- Work on the west side of the roadway began on June 19th.
- Veolia began replacing the water line on June 23rd. Work is on-going.
- ACHD’s contractor anticipates starting roadway and sidewalk work for Phase 2 on August 10th.
-
2021
Liberty Street, Denton to Douglas has finished this stageDesign started
-
July 2022
Liberty Street, Denton to Douglas has finished this stageGather public input
-
2023
Liberty Street, Denton to Douglas has finished this stageBegin purchasing property necessary for project
-
November 2025
Liberty Street, Denton to Douglas is currently at this stageStart construction
-
Fall 2026
this is an upcoming stage for Liberty Street, Denton to DouglasConstruction is expected to be complete.*
-
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email connect@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org