Linder Overpass and Roadway Project, Franklin to Overland
The Ada County Highway District (ACHD) is constructing improvements for Linder Road between Franklin Road and Overland Road.
The project includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The project also extends Linder Road from Overland Road to the new overpass.
The Ada County Highway District (ACHD) is constructing improvements for Linder Road between Franklin Road and Overland Road.
The project includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The project also extends Linder Road from Overland Road to the new overpass.
-
October 10, 2025
Share October 10, 2025 on Facebook Share October 10, 2025 on X (formerly Twitter) Share October 10, 2025 on Linkedin Email October 10, 2025 link- Linder Rd. south side closure began June 12th
- Sidewalk ongoing
- Utility company working on moving facilities
- Project delayed until pole is relocated
- Anticipated week of the Oct 13th
- Linder Rd. south side closure began June 12th
- Sidewalk ongoing
- Utility company working on moving facilities
- Project delayed until pole is relocated
- Anticipated week of the Oct 13th
-
October 2, 2025
Share October 2, 2025 on Facebook Share October 2, 2025 on X (formerly Twitter) Share October 2, 2025 on Linkedin Email October 2, 2025 linkLinder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.
Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.
-
September 26, 2025
Share September 26, 2025 on Facebook Share September 26, 2025 on X (formerly Twitter) Share September 26, 2025 on Linkedin Email September 26, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Utility company working on moving facilities. Project delayed until pole is relocated. Pavement markings ongoing.
- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Utility company working on moving facilities. Project delayed until pole is relocated. Pavement markings ongoing.
-
September 19, 2025
Share September 19, 2025 on Facebook Share September 19, 2025 on X (formerly Twitter) Share September 19, 2025 on Linkedin Email September 19, 2025 linkLinder Rd. south side closure began June 12th.
Sidewalk ongoing.
Utility company working on moving facilities.
Project delayed until pole is relocated.
Linder Rd. south side closure began June 12th.
Sidewalk ongoing.
Utility company working on moving facilities.
Project delayed until pole is relocated.
-
September 12, 2025
Share September 12, 2025 on Facebook Share September 12, 2025 on X (formerly Twitter) Share September 12, 2025 on Linkedin Email September 12, 2025 link- Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.
- Linder Rd. south side closure began June 12th. Sidewalk ongoing. Utility company working on moving facilities. Project delayed until pole is relocated.
-
September 5, 2025
Share September 5, 2025 on Facebook Share September 5, 2025 on X (formerly Twitter) Share September 5, 2025 on Linkedin Email September 5, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
- Anticipated paving September 4th.
- Concrete median after paving anticipated September 10th.
- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
- Anticipated paving September 4th.
- Concrete median after paving anticipated September 10th.
-
August 29, 2025
Share August 29, 2025 on Facebook Share August 29, 2025 on X (formerly Twitter) Share August 29, 2025 on Linkedin Email August 29, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
- Anticipated paving September 4th.
- Concrete medium after paving.
- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
- Anticipated paving September 4th.
- Concrete medium after paving.
-
August 21, 2025
Share August 21, 2025 on Facebook Share August 21, 2025 on X (formerly Twitter) Share August 21, 2025 on Linkedin Email August 21, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
-
August 15, 2025
Share August 15, 2025 on Facebook Share August 15, 2025 on X (formerly Twitter) Share August 15, 2025 on Linkedin Email August 15, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placing pole foundations starting August 18th on South side of Overland.
- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placing pole foundations starting August 18th on South side of Overland.
-
August 8, 2025
Share August 8, 2025 on Facebook Share August 8, 2025 on X (formerly Twitter) Share August 8, 2025 on Linkedin Email August 8, 2025 linkLinder Rd. south side closure began June 12th. Sidewalk ongoing. Excavating complete. Idaho Power relocating their utilities. Storm drain complete. Sidewalk on South Linder ongoing.
Linder Rd. south side closure began June 12th. Sidewalk ongoing. Excavating complete. Idaho Power relocating their utilities. Storm drain complete. Sidewalk on South Linder ongoing.

-
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org
-
2022
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageDesign started
-
March 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stagePublic input opportunity.
-
Summer 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageRefine design.
-
Fall 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageSecond opportunity for public feedback.
-
2024/2025
Linder Overpass and Roadway Project, Franklin to Overland has finished this stagePurchase property necessary for project.
-
Early 2025
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageConstruction Phase 1
The first phase will focus on constructing improvements at the Overland Rd and Linder Rd intersection and a portion of the new roadway that will extend from Overland Rd to I-84. Please note this work does not include the overpass structure or any road widening north of I-84. Construction for Phase 1 is currently planned to begin in 2026.
-
2026-2027
Linder Overpass and Roadway Project, Franklin to Overland is currently at this stageConstruction Phase 2
This phase includes the I-84 overpass and the widening of Linder Rd from I-84 to Franklin Rd.