Linder Overpass and Roadway Project, Franklin to Overland
The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.
The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.
The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.
The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.
-
August 21, 2025
Share August 21, 2025 on Facebook Share August 21, 2025 on Twitter Share August 21, 2025 on Linkedin Email August 21, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placed pole foundations.
- Placing curb and gutter south of Overland.
-
August 15, 2025
Share August 15, 2025 on Facebook Share August 15, 2025 on Twitter Share August 15, 2025 on Linkedin Email August 15, 2025 link- Linder Rd. south side closure began June 12th.
- Sidewalk ongoing.
- Idaho Power relocating their utilities.
- Placing pole foundations starting August 18th on South side of Overland.
-
August 8, 2025
Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 linkLinder Rd. south side closure began June 12th. Sidewalk ongoing. Excavating complete. Idaho Power relocating their utilities. Storm drain complete. Sidewalk on South Linder ongoing.
-
August 1, 2025
Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 linkLinder Rd. south side closure began June 12th and will be in place through late July.
North side paved. Sidewalk ongoing. Excavating south side. Idaho Power relocating their utilities. Storm drain complete.
-
July 25, 2025
Share July 25, 2025 on Facebook Share July 25, 2025 on Twitter Share July 25, 2025 on Linkedin Email July 25, 2025 link- Linder Rd. south side closure began June 12th and will be in place through late July. North side paved.
- Sidewalk ongoing. Excavating south side. Idaho Power relocating their utilities. Storm drain complete.
-
July 18, 2025
Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link- Linder Rd. south side closure began June 12th and will be in place through late July
- North side paved
- Sidewalk ongoing
- Excavating south side
- Idaho Power relocating their utilities
- Storm drain ongoing
-
July 11, 2025
Share July 11, 2025 on Facebook Share July 11, 2025 on Twitter Share July 11, 2025 on Linkedin Email July 11, 2025 link- Irrigation complete.
- Retaining wall complete. Pole bases being placed.
- Linder Rd. south side closure began June 12th and will be in place through late July. North side paved. Sidewalk ongoing. Excavating south side.
-
July 2, 2025
Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link- Irrigation complete.
- Retaining wall complete.
- Pole bases being placed.
- Linder Rd. south side closure began June 12th and will be in place through late July. North side paved. Sidewalk ongoing. Excavating south side.
-
June 26, 2025
Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link- Irrigation Complete.
- Retaining wall complete.
- Pole bases being placed.
- Linder Rd. south side closure began June 12th and will be in place through late July.
- Curb being placed on north side of project.
- Removals ongoing on south side of project.
-
June 20, 2025
Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link- Irrigation Complete
- Retaining wall ongoing
- Pole bases being placed
- Linder Rd. south side closure began June 12th and will be in place through late July
- Curb being placed on north side of project
- Removals ongoing on south side of project
Follow Project
Who's Listening
-
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org
Timeline
-
2022
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageDesign started
-
March 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stagePublic input opportunity.
-
Summer 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageRefine design.
-
Fall 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageSecond opportunity for public feedback.
-
2024/2025
Linder Overpass and Roadway Project, Franklin to Overland has finished this stagePurchase property necessary for project.
-
Early 2025
Linder Overpass and Roadway Project, Franklin to Overland is currently at this stageConstruction Phase 1
The first phase will focus on constructing improvements at the Overland Rd and Linder Rd intersection and a portion of the new roadway that will extend from Overland Rd to I-84. Please note this work does not include the overpass structure or any road widening north of I-84. Construction for Phase 1 is currently planned to begin in early 2025.
-
Late 2026
this is an upcoming stage for Linder Overpass and Roadway Project, Franklin to OverlandConstruction Phase 2
This phase includes the I-84 overpass and the widening of Linder Rd from I-84 to Franklin Rd.