Linder Overpass and Roadway Project, Franklin to Overland

Share Linder Overpass and Roadway Project, Franklin to Overland on Facebook Share Linder Overpass and Roadway Project, Franklin to Overland on Twitter Share Linder Overpass and Roadway Project, Franklin to Overland on Linkedin Email Linder Overpass and Roadway Project, Franklin to Overland link

The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.

The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.

The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.

The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.

  • August 21, 2025

    Share August 21, 2025 on Facebook Share August 21, 2025 on Twitter Share August 21, 2025 on Linkedin Email August 21, 2025 link
    • Linder Rd. south side closure began June 12th.
    • Sidewalk ongoing.
    • Idaho Power relocating their utilities.
    • Placed pole foundations.
    • Placing curb and gutter south of Overland.
  • August 15, 2025

    Share August 15, 2025 on Facebook Share August 15, 2025 on Twitter Share August 15, 2025 on Linkedin Email August 15, 2025 link
    • Linder Rd. south side closure began June 12th.
    • Sidewalk ongoing.
    • Idaho Power relocating their utilities.
    • Placing pole foundations starting August 18th on South side of Overland.
  • August 8, 2025

    Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 link

    Linder Rd. south side closure began June 12th. Sidewalk ongoing. Excavating complete. Idaho Power relocating their utilities. Storm drain complete. Sidewalk on South Linder ongoing.

  • August 1, 2025

    Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 link

    Linder Rd. south side closure began June 12th and will be in place through late July.

    North side paved. Sidewalk ongoing. Excavating south side. Idaho Power relocating their utilities. Storm drain complete.

  • July 25, 2025

    Share July 25, 2025 on Facebook Share July 25, 2025 on Twitter Share July 25, 2025 on Linkedin Email July 25, 2025 link
    • Linder Rd. south side closure began June 12th and will be in place through late July. North side paved.
    • Sidewalk ongoing. Excavating south side. Idaho Power relocating their utilities. Storm drain complete.
  • July 18, 2025

    Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link
    • Linder Rd. south side closure began June 12th and will be in place through late July
    • North side paved
    • Sidewalk ongoing
    • Excavating south side
    • Idaho Power relocating their utilities
    • Storm drain ongoing
  • July 11, 2025

    Share July 11, 2025 on Facebook Share July 11, 2025 on Twitter Share July 11, 2025 on Linkedin Email July 11, 2025 link
    • Irrigation complete.
    • Retaining wall complete. Pole bases being placed.
    • Linder Rd. south side closure began June 12th and will be in place through late July. North side paved. Sidewalk ongoing. Excavating south side.
  • July 2, 2025

    Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link
    • Irrigation complete.
    • Retaining wall complete.
    • Pole bases being placed.
    • Linder Rd. south side closure began June 12th and will be in place through late July. North side paved. Sidewalk ongoing. Excavating south side.
  • June 26, 2025

    Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link
    • Irrigation Complete.
    • Retaining wall complete.
    • Pole bases being placed.
    • Linder Rd. south side closure began June 12th and will be in place through late July.
    • Curb being placed on north side of project.
    • Removals ongoing on south side of project.
  • June 20, 2025

    Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link
    • Irrigation Complete
    • Retaining wall ongoing
    • Pole bases being placed
    • Linder Rd. south side closure began June 12th and will be in place through late July
    • Curb being placed on north side of project
    • Removals ongoing on south side of project
Page last updated: 03 Nov 2025, 08:40 AM