Linder Overpass and Roadway Project, Franklin to Overland
The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.
The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.
The Ada County Highway District (ACHD) is designing future improvements for Linder Road between Franklin Road and Overland Road.
The proposed design includes an overpass spanning Interstate 84 and widening Linder Road to include additional travel lanes and facilities for those that walk, bike and roll. The design also proposes extending Linder Road from Overland Road to the new overpass.
-
June 13, 2025
Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link- Irrigation complete.
- Retaining wall ongoing.
- Pole bases being placed.
- Linder Rd. south side closure began June 12th and will be in place through late July.
-
June 6, 2025
Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link- Irrigation complete.
- Retaining wall ongoing.
- Pole bases being placed.
- Linder Rd. south side anticipated closure beginning June 16th.
-
May 30, 2025
Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link- Irrigation complete.
- Retaining wall ongoing.
- Utility work ongoing.
-
May 23, 2025
Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link- Irrigation complete.
- Retaining wall ongoing.
-
May 16, 2025
Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link- Irrigation complete.
- Retaining wall ongoing.
-
May 8, 2025
Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link- Irrigation complete.
- Storm drain being installed.
- Excavating and prepping for wall on Linder.
- Retaining wall ongoing.
-
May 2, 2025
Share May 2, 2025 on Facebook Share May 2, 2025 on Twitter Share May 2, 2025 on Linkedin Email May 2, 2025 link- Irrigation Complete.
- Storm drain being installed.
- Excavating and prepping for wall on Linder.
-
April 25, 2025
Share April 25, 2025 on Facebook Share April 25, 2025 on Twitter Share April 25, 2025 on Linkedin Email April 25, 2025 link- Irrigation complete.
- Storm drain being installed.
- Excavating and prepping for wall on Linder.
-
April 11, 2025
Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 link- Irrigation started on southwest corner.
-
April 4, 2025
Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link- Notice to proceed is anticipated for April 7th.
- Starting irrigation on southwest corner.
Follow Project
Who's Listening
-
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org
Timeline
-
2022
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageDesign started
-
March 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stagePublic input opportunity.
-
Summer 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageRefine design.
-
Fall 2023
Linder Overpass and Roadway Project, Franklin to Overland has finished this stageSecond opportunity for public feedback.
-
2024/2025
Linder Overpass and Roadway Project, Franklin to Overland has finished this stagePurchase property necessary for project.
-
Early 2025
Linder Overpass and Roadway Project, Franklin to Overland is currently at this stageConstruction Phase 1
The first phase will focus on constructing improvements at the Overland Rd and Linder Rd intersection and a portion of the new roadway that will extend from Overland Rd to I-84. Please note this work does not include the overpass structure or any road widening north of I-84. Construction for Phase 1 is currently planned to begin in early 2025.
-
Late 2026
this is an upcoming stage for Linder Overpass and Roadway Project, Franklin to OverlandConstruction Phase 2
This phase includes the I-84 overpass and the widening of Linder Rd from I-84 to Franklin Rd.